NO.109 The business analyst generated a design specification for a new product. What is the best type of formal review to conduct with the customer to establish an approved requirements baseline?

 
 
 
 

NO.110 Which function involves auditing both the quality requirements to resolve discrepancies and the results of quality control measurements to ensure that appropriate quality standards and operational definitions are being used?

 
 
 
 

NO.111 Which of the following is the best approach to enable developers and product owners to be in constant communication so that changes or issues that occur during development are exposed and discussed as they develop?

 
 
 
 

NO.112 Which of the following actions will contribute most to the success of the initial stage of the project?

 
 
 
 

NO.113 Which statement accurately depicts what changes can be made to requirements after they are baselined?

 
 
 
 

NO.114 The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.
Which course of action should the business analyst take?

 
 
 
 

NO.115 A project affects the marketing unit and procurement unit. The project manager gives the business analyst an overview of the project for the first time.
What should the business analyst do immediately after the discussion?

 
 
 
 

NO.116 A business analyst is working on a project’s acceptance criteria. In an early collaboration with the company’s stakeholders, the business analyst identified several user groups within the company: “Purchaser,” “Shipper,”
“Customer,” and “Agent”. The user groups categorize stakeholders with similar needs and create a detailed narrative.
Which technique did the business analyst use for evaluating the solution’s acceptance criteria?

 
 
 
 

NO.117 A business analyst needs to estimate the effort associated with project requirements. However, the lack of detail is concerning. What technique could the business analyst use to help alleviate this concern?

 
 
 
 

NO.118 A company has completed a major project within time, cost, and scope and satisfied high-level quality standards and marketing requests. However, the product was considered a complete failure by shareholders and the market due to low return on investment.
From the business analysis perspective, the main reason for this business failure was a failure to:

 
 
 
 

NO.119 A business analyst from Company A has been assigned a project to document and identify requirements for a new commercial software implementation. The first step is to break down the business analysis deliverables into activities and tasks. Then, the business analyst will add an estimate of the time needed to complete the work.
Which type of estimation technique is the business analyst using?

 
 
 
 

NO.120 A business analyst for Company A has been assigned to a three-year project to assist health insurance Company B with implementing and testing a new set of medical codes. The business analyst has identified many stakeholders who will participate in the project. For example, Company A will designate technical staff to write and code the requirements and provide a testing team to test the new functionality. The senior director of Company B will require weekly progress updates. The project manager from Company A will create project plans, schedule meetings, and provide meeting minutes.
In the scenario above, what is the role of the technical staff and testing team from Company A?

 
 
 
 

NO.121 How can a business analyst show progressive iterations of product development to stakeholders after the requirements baseline has been approved?

 
 
 
 

NO.122 A business analysis team has collected the mam business requirements from the major stakeholders of a project. The team wants to be sure that each stakeholder has a clear understanding of the areas of analysis that will be in scope.
Which model should the team employ to ensure the most effective representation of analysis boundary?

 
 
 
 

NO.123 The business analyst is in the process of implementing a solution for a customer. The team is having difficulty confirming if certain requirements have been met.
What could have caused this issue?

 
 
 
 

NO.124 The document that defines the process for managing requirements revisions is the:

 
 
 
 

NO.125 In order to reduce product and project risk for a large, complex project, a business analyst is asked to help develop a change process that includes formal authorization and tracking throughout the life cycle of the project. The business analyst needs a capability that will help ensure that the product conforms to approved requirements, changes can be documented, and the status of each change can be reported.
What should the business analyst use?

 
 
 
 

NO.126 A business analyst in organization Y is assigned to elicit requirements in a project within a defined timeline. The business analyst has identified and invited key stakeholders to a requirements workshop. However, the stakeholders are not giving clear and concise requirements; their opinions about requirements are changing and conflicting with each other in the meeting. In the end, the business analyst could not elicit and define the requirements and therefore adjourned the meeting.
Which tool or technique could have been used by business analyst to avoid this situation?

 
 
 
 

NO.127

 
 
 
 
 

NO.128 The business analyst wants to ensure that requirement changes can be formally tracked after the product is baselined. What will the business analyst need to evaluate the proposed change?

 
 
 
 

NO.129 What should be done lo ensure that the product design meets the stated requirements?

 
 
 
 

NO.130 The project sponsor needs lo know which requirements will be implemented. Which of the following would be the most valuable for a business analyst to provide?

 
 
 
 

NO.131 Which of the following is a method for requirements change control?

 
 
 
 

NO.132 After completing the requirements, the project manager and business analyst realize that the project scope is not feasible in the projected schedule The business analyst needs to review the amount of work the team is capable of delivering based on the approved project schedule.
Which prioritization technique should the business analyst use?

 
 
 
 

NO.133 A project team has completed the system use cases along with accompanying screen mockups. The business analyst schedules a review meeting with the client team to walk through the artifacts.
What is the purpose of this meeting?

 
 
 
 

PMI PMI-PBA Practice Test Questions, PMI PMI-PBA Exam Practice Test Questions

The PMI Professional in Business Analysis (PMI-PBA) certification is created to validate the candidates’ expertise in business analysis and using the relevant tools and techniques to enhance the overall success of projects. It equips the applicants with the essential knowledge and skills required to satisfy the needs of organizations that rely on the business analysis specialists to play key roles in their teams. To get this certificate, the individuals should meet several requirements, including business analysis training, experience working on projects, and passing one qualifying exam.

 

100% Free PMI-PBA Daily Practice Exam With 202 Questions: https://www.2pass4sure.com/PMI-Professional-in-Business-Analysis/PMI-PBA-actual-exam-braindumps.html

         

Related Links: www.stes.tyc.edu.tw www.stes.tyc.edu.tw www.stes.tyc.edu.tw www.stes.tyc.edu.tw www.stes.tyc.edu.tw www.stes.tyc.edu.tw