NEW QUESTION 18
Material
You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason?
Note : there are 2 correct answers for this question.

 
 
 
 

NEW QUESTION 19
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question

 
 
 
 

NEW QUESTION 20
You want to use subnetworks during the project. Which of the following statements describes subnetworks?

 
 
 
 

NEW QUESTION 21
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.

 
 
 
 

NEW QUESTION 22
Which of the following apply to dynamic item processor (DIP)? Note: There are 3 correct Answers to this question.

 
 
 
 
 

NEW QUESTION 23
Which of the following apply to dynamic item processor (DIP)? Note: There are 3correct answers to this question.

 
 
 
 
 

NEW QUESTION 24
Project Structure
Your customer has implemented budgeting for projects. The current budget of their projects has been changed several times.
Therefore they want to get an overviews of the budget updates.
What standard report do you recommend?

 
 
 
 

NEW QUESTION 25
What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this question

 
 
 
 

NEW QUESTION 26
Where can you define a network as “header-account-assigned” or “activity-account-assigned”?

 
 
 
 

NEW QUESTION 27
Your customer has created networks with internal activities and generated capacity requirements. Now,
they want to analyze the capacity requirements of their project. Which report do you recommend?

 
 
 
 

NEW QUESTION 28
You are working with networks and WBS elements. Which of the following statements applies?

 
 
 
 

NEW QUESTION 29
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?

 
 
 
 

NEW QUESTION 30
You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?

 
 
 
 

NEW QUESTION 31
Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.

 
 
 
 

NEW QUESTION 32
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

 
 
 
 
 

NEW QUESTION 33
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?

 
 
 
 