The CompTIA PK0-004 exam is associated with the Project+ certification that is designed for the business practitioners who are responsible for managing small- and medium-sized projects, both within the Information Technology sphere and outside it. After passing this test, the candidates gain the expertise needed to manage the project lifecycle; guarantee proper communication; manage the stakeholders & resources; and handle project documentation.

 

QUESTION 399
A vendor has accepted a proposed project from a customer.
Which of the following is MOST likely to be the first document created by the project manager?

 
 
 
 

QUESTION 400
During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project.
Which of the following documents would contain these items?

 
 
 
 

QUESTION 401
Which of the following information does the project risk register typically contain?

 
 
 
 

QUESTION 402
A customer will have ongoing changes to project requirements.
Which of the following is the BEST project management methodology for this requirement?

 
 
 
 

QUESTION 403
A cost baseline is used to measure the:

 
 
 
 

QUESTION 404
A company has dictated project scope changes but has stated that the original budget still applies. Which of the following will MOST likely be impacted by the changes?

 
 
 
 

QUESTION 405
A project manager determines deliverables are not meeting customer specifications. During which of the following project phases is this determination MOST likely to happen?

 
 
 
 

QUESTION 406
As part of a project, employee production cannot proceed unless certain thresholds of the product are achieved. Which of the following is this called?

 
 
 
 
 

QUESTION 407
A project sponsor wants to demonstrate progress on a deliverable to all stakeholders at the next tollgate meeting. This feature was not scheduled for this tollgate, but the project manager plans to add it to the next phase. Which of the following describes what the project manager is doing?

 
 
 
 

QUESTION 408
A project requires daily status updates.
Which of the following is the MOST effective method for providing these updates?

 
 
 
 

QUESTION 409
A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries.
Which of the following documents should the project manager create?

 
 
 
 

QUESTION 410
Project team members have stated that they are having difficulty reaching the newly available corporate resources, and any response comes at unusual hours. Which of the following is MOST likely the cause?

 
 
 
 

QUESTION 411
A fire occurred in the production facility over the weekend, affecting the machinery being used to produce a deliverable. No injuries were reported.
Which of the following is MOST appropriate for the project manager to do NEXT?

 
 
 
 

QUESTION 412
An active project has a CPI of 0.92. Which of the following can be determined?

 
 
 
 

QUESTION 413
A procurement project manager presents the project status at a steering committee review. One of the defined risks is becoming an issue. The steering committee provides feedback and agrees on a mitigation plan. After reviewing the meeting minutes and project documents, a new risk is created. Which of the following needs to occur FIRST?

 
 
 
 

QUESTION 414
A project manager is creating the WBS.
In which of the following phases is the project?

 
 
 
 

QUESTION 415
Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3.
Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a duration of one day. Which of the following represents the critical path?

 
 
 
 